Apr
02

Judicial Review Of The Irish Renewable Energy Programme -An Analysis

The High Court

By Pat Swords, Turn 180

‘A test case in relation to Citizens’ Rights in Ireland and Environmental Democracy’

Contents

1.      Background.

2.      The Compliance Investigation at the UNECE Legal Tribunal

3.      The Resulting Judicial Review in the High Court

4.      Access to Justice under EU Law and your Rights under the Convention.

5.      Ireland – Access to Information on the Environment

6.      Ireland – Public Participation in Decision-Making.

7.      Ireland – Access to Justice.

8.      Conclusions.

1.  Background

The Judicial Review in the Irish High Court scheduled for the 13th March 2013 has been adjourned until the 11th April. The Irish State submitted a more detailed Affidavit on the 7th March, which required additional work to respond to and the Court deferred the hearing to allow for an additional Affidavit to be prepared and for the exchange of submissions one week before the hearing.

What is clear is that this case goes to the heart of the Citizen’s rights and to the principle; Quis custodiet ipsos custodes? (Who watches the watchmen?). Can Irish law continue to operate outside the framework of European Community legislation and Treaty arrangements with the United Nations; in particular as Ireland has since June 2012 ratified the United Nations Economic Commission for Europe’s (UNECE) Aarhus Convention on Access to Information, Public Participation in Decision-Making and Access to Justice in Environmental Matters?

Can this renewable energy programme, with its enormous financial costs and impacts on the environment be forced through by an administration in a manner, which is clearly outside of the law? To which one could add, the abject failures to demonstrate the effectiveness of the renewable technology chosen, i.e. wind energy, and the reasons for selecting it as suitable to receive billions in State Aid funding. A situation, in which the lack of transparency and accountability is so extreme, that one can only conclude that the system is wide open, not just to the pressure of lobbying, but to the possibility of corruption.

One can also ask what should be the most obvious question – how long are Irish citizens going to tolerate an administration, which actively subverts their democratic rights and uses considerable sums of their taxpayers’ funds to do so? Do they care that they have been effectively been ‘shut out’ of their rights in relation to the decision-making around them and that their State officials will do everything, including operating outside the legal framework, to ensure that this is the situation which remains?

2.  The Compliance Investigation at the UNECE Legal Tribunal

Normally a Judicial Review would be dismissed if not brought within the specified time, but in my case the legal framework wasn’t there to allow such a challenge when Ireland’s National Renewable Energy Action Plan was notified on the 30th June 2010 to the EU Commission.

Instead the matter went to the Compliance Committee of the UNECE Aarhus Convention, where the Committee investigated the EU’s compliance with its obligations under the Convention in relation to the implementation of the 20% renewable energy by 2020 Directive in Ireland. This case at the Compliance Committee could not be taken against Ireland, as the Irish State had not then ratified the Convention, the only one of the 27 Member States not to do so. However, the EU had ratified the Convention in February 2005 and and in September 2007 the position of the Aarhus Convention on Community legal order in Ireland was clarified by the EU to the UNECE Compliance Committee[1], i.e. in theory it applied to Ireland through Community legal order. The communication was therefore submitted in October 2010 against the EU as a Party to the Convention and the Committee then initiated a compliance investigation with regard to the EU’s legal obligations under the Convention.

In its Affidavit to the High Court as part of the Judicial Review[2], the Department of Energy, Communications and Natural Resources declared that the State:

  • Was not a Party to the Committee’s proceedings, and was not heard, and the findings of the Committee were against the EU only”.

The facts of the matter are widely different to the above. Firstly, the Irish State was not only present as an observer at the Compliance Committee meeting in September 2011 in Geneva, but refused to offer any comments when offered the opportunity to do so by the Committee.

Secondly, the State actively participated in preparing the documentation for submittal by the EU to the Committee, a point known by the official, who swore the above affidavit, as correspondence previously obtained in late 2011 under the Access to Information on the Environment regulations demonstrated that she herself had actively assisted in preparing this documentation. Indeed the letter of the 23rd February 2011 from the Department of the Environment, Community and Local Government (John McCarthy, Assistant Secretary) to the Department of Energy, Communications and Natural Resources (Sarah White, Deputy Secretary) is highly revealing in this context:

  • “As you will be aware from previous communications, Ireland is the only EU Member State which has not ratified the Aarhus Convention. However, as the EU is a Party to the Convention in its own right, it has certain obligations, not least an obligation to cooperate with the Aarhus Compliance Committee (ACC) on issues such as this. While we are anxious to avoid creating legal precedence by engaging directly with the ACC until such time as the Convention is ratified, nonetheless it is critical that the State cooperates fully with the Commission as it investigates this matter”.

In August 2012, the Compliance Committee ruled against the EU in that the implementation of the renewable energy programme had by-passed the necessary procedures in relation to environmental assessment and democratic accountability[3]. Since then both Ireland and the EU have refused to comply with the recommendations of the Compliance Committee, which requires providing the public with the necessary information, completing the required public participation in decision making on the National Renewable Energy Action Plan when all options are open and taking due account of the public participation in the final decision.

3.  The Resulting Judicial Review in the High Court

As a result of these illegalities, there was no option but to take the current National Renewable Energy Action Plan, and associated funding arrangement REFIT, into the Irish High Court for a Judicial Review. In response, the position the State is now adopting is that it has legitimacy to continue with the renewable programme, as (a) nobody initiated a Judicial Review in the High Court back in 2010 and; (b) because it does not recognise the findings and recommendations of the Compliance Committee of the Convention it has itself ratified. In layman’s terms; I can murder my wife and if you don’t take me to Court within x months, regardless of the fact that because of my actions the Court is not accessible to you, then I’m automatically innocent and can continue as I choose.

On my side my ‘defence’ is novel; nobody before in an Irish legal case has presented such a ruling from this international legal tribunal, a ruling which is associated with a history of refusal by the State to comply with the Convention and the associated framework of EU law. A Convention, which is not only an International Treaty, but also recognises that the environment does not belong to the State administration, but rather to the Citizens, who have to be provided with procedural rights; in other words environmental democracy. It is a somewhat complex situation, described now in further detail for those, who wish to be informed further.

4.  Access to Justice under EU Law and your Rights under the Convention

In February 2005 the EU ratified the UNECE Aarhus Convention through Decision 2005/370[4]. In ratifying the Convention, two Directives to the Member States were referred to; namely Directive 2003/4/EC on access to information on the environment and Directive 2003/35/EC on public participation. Directive 2003/4/EC is relatively straightforward in legal terms, as it transposed the first pillar of the Convention on access to and dissemination of environmental information.

The second Directive on public participation was more complex. Firstly it modified the cornerstone for planning approval of all medium and large scale projects, namely the Directive on Environmental Impact Assessment. Secondly it modified the environmental permitting of larger industrial facilities through the Directive on Integrated Pollution Prevention and Control. For both Directives, the citizen’s rights were defined not only in relation to public participation procedures, but also in relation to procedures for access to justice, in that one had to be provided with recourse to legal procedures in a court of law, which are fair, equitable, timely and not prohibitively expensive to “challenge the substantive or procedural legality of decisions, acts or omissions subject to the public participation provisions of this Directive”.

While under Community law such access to justice provisions was essentially only specifically directed at these two key EU Directives on planning and environmental permits, this fell a long way short of what the Aarhus Convention required in its Article 9(3), namely that a Party to the Convention shall ensure:

  • “Members of the public have access to administrative or judicial procedures to challenge acts and omissions by private persons and public authorities which contravene provisions of its national law relating to the environment”.

To clarify, the access to justice provisions in the Convention is not just limited to the acts and omissions of the authorities in relation to planning and environmental permits, but is broadened to a far wider scope to include the acts and omissions of private persons and with regard to challenging acts and omissions in relation to all aspects of environmental law. Simply put, with regard to matters related to environmental law, it solves ‘who watches the watchman’, as it gives the citizen the ‘tool box’ to ensure the necessary enforcement by himself or herself.

However, in ratification of the Aarhus Convention in February 2005, the EU ‘kicked to touch’; a Directive on access to justice could not be agreed on, so:

  • “European Community also declares that the legal instruments in force do not cover fully the implementation of the obligations resulting from Article 9(3) of the Convention as they relate to administrative and judicial procedures to challenge acts and omissions by private persons and public authorities other than the institutions of the European Community as covered by Article 2(2)(d) of the Convention, and that, consequently, its Member States are responsible for the performance of these obligations at the time of approval of the Convention by the European Community and will remain so unless and until the Community, in the exercise of its powers under the EC Treaty, adopts provisions of Community law covering the implementation of those obligations”.

The Irish State not only sought to take advantage of the legislative vacuum above in relation to environmental democracy, but to actively ensure that its citizens were denied the rights bestowed upon them in relation to the two Member State Directives on access to information and public participation. While the Irish State was by far the worst Member State in relation to failures to comply with the above legislative requirements, less than compliant practices also occurred elsewhere. However, it is useful to go through the three Pillars of the Convention, on information, public participation in decision-making and access to justice and document where the position stands in Ireland.

5.  Ireland – Access to Information on the Environment

Firstly while the Irish State finally transposed the relevant Directive 2003/4/EC in March 2007 by means of S.I. No 133 of 2007[5], more than two years after it was required to do so by Community law, it did not transpose it properly. In December 2011, the State had to make the necessary amendments through S.I. No. 662 of 2011, in particular with regards to the dissemination of information on the environment and that a public authority shall:

  • “Ensure that environmental information compiled by or for it, is up-to-date, accurate and comparable”

However, the ‘state of play’ with the regulations in Ireland can be best described as, if you go looking for environmental information, which they want to give you, then things generally run smoothly. If on the other hand you step out of their comfort zone, then public authorities will simply start engaging in an increasing amount of obstruction, even to the point of unlawful behaviour.

In principle under Article 9(1) of the Convention, the Citizen has to have access to an independent appeals process, if the citizen’s request for information has been ignored, wrongfully refused, whether in part or in full, inadequately answered, or otherwise not dealt with in accordance with the provisions of the Convention. This appeals procedure has to be fair, equitable, timely and not prohibitively expensive. In Ireland, there is a Commissioner for Environmental Information, which is part of the remit of the Ombudsman. As she herself states in her 2011 Report[6]:

  • “Moreover, despite the general duties placed on public authorities to facilitate access to environmental information, a general lack of awareness seems to persist among the public regarding their rights under the Regulations. My staff continue to be in communication with the Department in relation to the operation of the Regulations and have noted in particular that it is of some considerable concern to me that the level of awareness both by the public and public authorities remains very low”.

While the Convention, EU and National law require public authorities to:

  • “Inform the public of their rights under these Regulations and provide information and guidance on the exercise of those rights”.

The reality is that this has not occurred. In fact experience has shown that the Department of the Environment itself is actively engaged in obstructing access to information about its activities.

With regard to taking appeals to the Commission for Environmental Information, this has a cost of €150 and takes between six months and over eighteen months for an appeal to be resolved. This certainly is not timely and is acting as a major disincentive for people seeking recourse to justice. Indeed, since the introduction of the regulations in 2007, the Commissioner has only resolved 25 appeals[7]. Furthermore, in her latest report, she is making it clear she doesn’t have the resources to process them. It is however interesting to examine a number of these appeals.

In CEI/07/0005 the Department of the Taoiseach[8] (Prime Minister) refused to provide access to documentation on emissions, citing Cabinet Confidentiality under the Constitution. However, Directive 2003/4/EC and the Convention are clear in that no exemptions apply in relation to emissions, this information must be publically available. The Department of the Taoiseach instead of then making the information available, spent considerable funds of taxpayers’ money contesting the matter in the High Court, from which the case has now gone to the Supreme Court, the critical issue being the manner in which the Irish regulations do not properly transpose the EU Directive.

The recent (February 2013) case in the High Court in relation to the National Asset Management Authority (NAMA) is also revealing[9]. When NAMA was set up following the financial crises in Ireland to manage the assets of bankrupt property developers, it was exempt from the Freedom of Information legislation. However, it was as a public authority not exempt from the Convention and the EU and National law implementing it. Despite this it refused to comply with requests for information on the environment and the resulting decision of the Commissioner, which followed an appeal from a member of the public. Instead it contested the Commissioner’s decision in the High Court, where it lost, but not having first incurred €121,350 of legal costs[10], which had to be funded by the taxpayer, to whom it was using their money to subvert their rights. Additional legal costs would have been incurred by the Commissioner.

In Case CEI/10/0002 information was requested from An Bord Pleanala (the planning appeals board)[11]. Under the Convention and the Environmental Impact Assessment Directive, the competent authority for the planning decision has to make available the “the main reports and advice” issued to it. The outcome of the appeal was that the Commissioner ruled that no such information in relation to risk was held by An Bord Pleanala with regard to the Corrib Gas Pipeline it was assessing; a planning decision, which it conducted in a most unprofessional manner outside of the legal framework. As it turned out some months after the outcome of the appeal, such documentation as had been previously legally requested became publically available. When this was pointed out to the Commissioner for Environmental Information, her response was that there had been a two month period after her decision to appeal it to the High Court, which had not been exercised. Clearly An Bord Pleanala had no respect for the law that applied to them or the office of the Commissioner for Environmental Information.

Another equally sad feature that is reoccurring is that even when it can be documented that public authorities are disseminating blatantly false information or fail to have information, which they are legally required to have, no action is taken. In CEI/11/0003 in relation to the Department of Communications, Energy and Natural Resources, the Green Party Minister for Energy Eamon Ryan made claims on prime time TV that wind energy would reduce the costs for consumers and repeatedly stated that his department had national and international reports to confirm this. The subsequent request for information determined that no such reports existed; indeed the two provided in relation to the Irish situation, both had as a base case an installed capacity of 2,000 MW of wind energy and never even assessed the performance of the grid without this considerable investment in wind energy.

As far as the Department was concerned, it was the “Minister’s prerogative to draw the conclusions he deemed appropriate from the reports and other information available to him”. In reality, once the Minister assumes office, he is a member of the public authority and he is bound by its legal framework, in that information on the environment, which includes that given orally, has to be ‘up to date, accurate and comparable’. Unfortunately, such circumstances are routine, with the result is that the public are grossly misinformed about the environment around them and are not in a position to actively participate in the decision-making which occurs.

6. Ireland – Public Participation in Decision-Making

Public participation in decision making is a complete farce in Ireland; if it does occur at all it is simply the collection of submissions, which are then ignored; the decision having already been made by those in authority. If we consider the findings of the Compliance Committee referred to earlier in relation to the National Renewable Energy Action Plan and the public participation which occurred:

  • “It was conducted within a very short time frame, namely two weeks. Public participation under article 7 of the Convention must meet the standards of the Convention, including article 6, paragraph 3, of the Convention, which requires reasonable time frames. A two week period is not a reasonable time frame for “the public to prepare and participate effectively”, taking into account the complexity of the plan or programme[12]”.

In their Affidavit to the Court on the Judicial Review, the State made it clear[13] that:

  • “The process for ensuring sufficient grid connection to meet the 2020 target and the type of renewable energy concerned was decided well in advance of and before the submission of Ireland’s National Renewable Energy Action Plan in July 2010”.

To put this in context, the two week public consultation, which was held between the 11th June and 25th June, just before the notification date to the Commission on the 30th June 2012, never actually ‘mattered a dam’; it was all a done deal. If we consider the ‘Aarhus Convention: An Implementation Guide’, this is very clear in Page 109 in relation to how “each Party shall ensure that in the decision due account is taken of the outcome of the public participation[14]”.

  • “The relevant authority is ultimately responsible for the decision based on all information, including comments received, and should be able to show why a particular comment was rejected on substantive grounds”.

This is extremely important, as the guide puts it; “in appropriate circumstances a member of the public whose comments were not duly taken into account will be able to challenge the final decision in an administrative or judicial proceeding on this basis”. In essence it is this procedure which differentiates simply consulting with the public, i.e. telling them what we are doing, from what is the legally required public participation in decision-making, a key element of environmental democracy and the rights of the citizen.

However, despite a legal request for the documentation in which the Department of Communications, Energy and Natural Resources took account of the public participation on the National Renewable Energy Action Plan, there has been a refusal to provide any, a recurring theme with the farce that is public participation in Ireland.

Indeed, European law is quite specific, while Article 7 of the Convention requires that the ‘necessary information’ be provided to the public, Directive 2001/42/EC on Strategic Environmental Assessment requires that the plan or programme be subject to a process of Strategic Environmental Assessment, which is not only a key element in democratic accountability and public participation, but it ensures that:

  • The environmental objectives of the programme are clearly defined.
  • The alternatives to achieve those objectives are also defined.
  • The likely state of evolution of the environment without implementation of the plan or programme is assessed.
  • The impacts of the programme on the environmental factors, such as population, human health, biodiversity, landscape, climate, etc, are assessed.
  • The appropriate mitigation measures are identified in relation to the impacts above.
  • The programme is monitored for unforeseen adverse effects during its implementation phase.

In other words, it is about proceeding with due care and attention, ensuring that the programme is appropriate and proportionate. However, none of this was completed in Ireland for the renewable energy programme[15], a position which led the UNECE Aarhus Compliance Committee to accept Communication ACCC/C/2010/54 and initiate a compliance investigation.

Unfortunately, as history shows us, when a vacuum is created by the lack of defined and transparent procedures, then political agendas and exploitation of the circumstances occur, so too with the renewable energy programme. There are eleven different sources of renewable energy listed in Directive 2009/28/EC. In particular, it is internationally recognised that Waste to Energy plants can result in CO2 abatement cost of a third of that for wind[16]. However, the coalition Government, which was in power up until early 2011 contain the Green Party, which was vehemently against such Waste to Energy plants. Unfortunately, the Department of the Environment acted according to their Green Party Minister John Gromely’s wishes to essentially put these legitimate businesses out of operation.

Firstly, they prepared their waste policy documentation utilising the services of the two companies, Eunomia and TBU, which prepared similar documentation for Greenpeace. The documentation was highly deficient. They then went to public participation on their Strategic Environmental Assessment and their programme to apply punitive levies on waste to energy plants. When the consultation closed, they refused to provide access to the Submissions received. This was appealed and finally resulted in the Submissions being posted on the website. The Submissions from the Environmental Protection Agency (EPA), the County & City Managers’ Association, the Regional Authorities for Waste Management and others pointed out that the proposed levies were not in compliance with EU legislation on waste management.

Despite this, a Bill had been published to introduce the levies on Waste to Energy[17] and was proceeding through the second house, the Seanad, when the Government fell. It was therefore requested in April 2011 that documentation be provided in relation to the ‘taking account of the public participation exercise’ and procedures in relation to such public participation in decision-making.

There was a refusal by the Department of the Environment to provide this information; instead they requested a fee estimated at €146 for ‘search and retrieval’. This was appealed to Commissioner for Environmental Information, who finally in February 2012 ruled that the charging of such a fee for ‘search and retrieval’ was not appropriate[18]. Despite this the Department are refusing to provide the relevant information citing as the reasons that they are considering appealing the Commissioner’s decision to the High Court.

A few months later with the new Government in place, the Department once again had a waste policy consultation and again it was requested that access to the submissions be provided and as to how ‘due account of the public participation would be taken in the final decision’. In their Reply AIE/2011/022 the Department stated:

  • “At this time, no such records exist. When such records are generated, it may be the case that they are considered to be non-releasable on grounds such as the need to protect Cabinet confidentiality and the wider policy making deliberative process”.

I never did receive them. Sadly the whole process is one of patronage, which is wide open to abuses, abuses which are occurring with regularity.

The same issues arise with public participation in decision making with the planning process. With the Corrib Gas planning process the scientific evidence didn’t matter a jot, a political agenda was at play and in their letter of 29th January 2010 to the developer, which never appeared on the public register, An Bord Pleanala defined the critical statement that revealed the standard to be applied for assessing the route for the pipeline was:

  • “The intent of the Board is to ensure that persons standing beside the dwellings will not receive a dangerous dose of thermal radiation in the worst case scenario of a “full bore rupture” of the pipeline at maximum pressure”.

Clearly this was the acceptance criteria in relation to risk. In effect several centuries of engineering experience in designing high pressure systems, such as guns or boilers, was completely irrelevant – it was going to completely split in two regardless. An Bord Pleanala were acting Ultra Vires by applying a condition, which was based solely on consideration of consequence, without any consideration of likelihood, the existing technical basis for design and approval of such piping systems and the experiences to date. The developer was left with no option after that letter of the 29th January, but to either bore a tunnel underground or bring An Bord Pleanala into the High Court. He chose to carry the cost of a tunnel, the reasons why will become clearer in the next section, at an estimated cost of €500 million, of which 25% represents lost revenue to the State.

StatoilHydro, who have a share in the this Corrib project in County Mayo, stated to the Media in August 2009, even before An Bord Pleanala refused to give planning permission to the final 9 km of pipeline:

  • “When we look at political risk with practical consequence to project progress then Ireland unfortunately stands out as an example”.

As the Irish Academy of Engineering stated in their March 2010 Submission to the Joint Oireachtas Committee on Climate Change and Energy Security:

  • When during the year the Chairman of Statoil publicly referred to the “political risk” of doing business in Ireland his comments would have been perceived by the international investment community as a major barrier to investment in Ireland. Political risk is what the oil industry normally associates with countries like Nigeria or Angola.[19]

The costs of essentially being a ‘banana republic’, in which a small entrenched elite dispense favours to their favourites, while putting those that are not their favourites at an enormous commercial disadvantage, have reached the situation, where the political risks of investing in Ireland are simply too high.

7.  Ireland – Access to Justice

As one moves from the first pillar of the Convention on information, through to the second pillar on public participation and finally to the third pillar on access to justice, the relative importance and significance rises; so too do the abject failures of the Irish State to comply, which is a deliberate feature and not occurring by accident. In Case C-427/07 Commission v Ireland[20], the Commission sought to address Ireland’s failure to comply with the requirement of ‘not prohibitively expensive’, with regard to the citizen’s right to challenge acts and omissions of public authorities in relation to planning and environmental permitting. Namely Directive 2003/35/EC as mentioned previously. These measures in relation to access to justice should have been in place by the 25th June 2005 by the latest.

The European Court in July 2009 found that the mere discretion of the Irish Courts to award costs after the event was not a valid implementation of the obligations in relation to ensuring the appellant’s rights in relation to ‘not prohibitively expensive’. Indeed Irish case law in the High Court on this issue had been pretty disastrous, in Friends of the Curragh Environment Limited v An Bord Pleanála [2006] IEHC 243[21], Justice Kelly declined to make a protective cost order available, instead stating with regard to the Directive’s requirement on ‘not prohibitively expensive’:

  • “The language is not sufficiently precise, clear or unconditional to render it of direct effect”.

Even worse happened in the case of Volkmar Klohn[22], who contested a planning decision adjacent to his organic farm in County Sligo, he was left not only with his own costs but also €86,000 of An Bord Pleanala’s costs. Justice Hedigan stating in May 2011 in relation to Article 29.6 of the Constitution, which provides that:

  • “No international agreement shall be part of the domestic law of the State save as may be determined by the Oireachtas.”
  • “With regard to the Aarhus Convention, this convention is not applicable as Ireland has not formally ratified it”.

Therefore, ‘not prohibitively expensive’ simply did not exist; one could not rely on the Aarhus Convention or even the European Legislation, which implemented it.

There is also the aspect of ‘standing’; could one get over this first threshold of a Court appearance, where one is required to demonstrate a justifiable reason for a full Court hearing? Under Irish law to achieve standing one had to demonstrate ‘substantial interest’ and ‘substantial grounds’ for seeking a Judicial Review. In Harding v Cork County Council [2008] IESC 27[23], the Supreme Court decided that in order to prove a substantial interest in an environmental planning case, an applicant must prove a peculiar and personal interest of significant weight which is affected by or connected with the development in question. This was in contravention to the Aarhus Convention, as it was too restrictive, and was finally updated by the Environment (Miscellaneous Provisions) Act of 2011, in which it was changed to ‘significant interest’.

Indeed despite the ratification of the Aarhus Convention on the 20th June 2012 and it taking effect ninety days later, the situation in relation to access to justice continues to be deplorable. Firstly, following the ruling of European Court in case C-427/07, the Planning and Development (Amendment) Act 2010[24], Section 33 specified for Judicial Reviews related to Directive 85/337/EEC on Environmental Impact Assessment, Directive 2001/42/EC on Strategic Environmental Assessment, Directive 2008/1/EC on Integrated Pollution Prevention and Control that each party (including any Notice Party) shall bear its own costs[25].

While, this may well have helped in that the Volkmar Klohn situation would not arise again, in that one would be forced to carry the costs of the planning authority, it fell far short of ‘not prohibitively expensive’. Clearly ‘inequality at arms’ still applied in that the State with unlimited resources could drag the case on for days and simply ‘burn out’ the appellant. Even worse, if in the past one had a very strong case there was the possibility that a lawyer would work ‘pro bono’, on the basis that if there was a win, the other side would pay the costs. Now under the new costs rules of each side pay their own, this was gone.

It wasn’t as if the State wasn’t warned about this and how these costs rules were a breach of the citizen’s rights, it was, it just chose to ignore it[26]. Amazingly it was the Green Party Minister of State for Planning, Ciaran Cuffe, who defended the State’s position in restricting access to justice to its citizen’s in environmental matters.

Not unsurprisingly in May 2012, the EU Commission commenced formal proceedings against the State yet again in relation to access to justice and Directive 2003/35/EC[27]. The problem is that these proceedings with the EU Commission take many years to have effect. Furthermore, one has to question the will and ability of the legal enforcement section of the Directorate General (DG) Environment, who in June 2009 were stating they were “prioritising work to improve access to justice in Ireland, which will include fresh infringement proceedings if necessary”[28]. Nearly four years later there is really no evidence of anything having been achieved.

Indeed on the 3rd December 2010, on my own expense and time, I went to Brussels to meet with officials of the EU Commission (DG Environment and DG Energy), to discuss the repeated abuses of EU environmental legislation, which were occurring in Ireland and related to the CHAP(2010)00645 complaints file. I considered their behaviour and response at the meeting to have been downright unprofessional, in particular in that I had to listen to Liam Chapman, Deputy Head of Unit ENV A.2, Compliance Promotion, Governance and Legal Issues, repeatedly ‘moaning’ about how difficult it was to take the Irish State into a legal process at the European Court of Justice, as they always had the best team of lawyers and fought every step of the way.

A clearer approach to the EU Commission’s view on Access to Justice can be seen from the fact that;

  • (a) not only was it criticised by the Aarhus Convention Compliance Committee for its procedures in relation to providing access for the EU citizens to challenge acts and omissions of the EU institutions in the European Court[29], but;
  • (b) the European General Court found it in breach of Community law on this point. Despite this, it is now using our taxpayer’s money to appeal this decision to the higher European Court of Justice[30].

Going back to the situation of the upcoming Judicial Review on the 11th April, the reality of the above is that back in June 2010 when the National Renewable Energy Action Plan was notified to the Commission:

  • Would one have got ‘standing’ to challenge the lack of public participation? Certainly the bar was set extremely high in relation to having to demonstrate ‘Substantial Interest’.
  • Was there any hope at all in relation to achieving ‘not prohibitively expensive’? Not only had Ireland failed to comply with the public participation Directive 2003/35/EC, but as the National Renewable Energy Action Plan related to a plan or programme on the environment connected with energy, it was not addressed by this Directive. Instead it was connected to Directive 2001/42/EC on Strategic Environmental Assessment and Article 7 of the Convention[31]. As such it would have to be enforced by the general provisions of Article 9(3) of the Convention, a Convention which Ireland refused to recognise.

The only certainty with the above was that there was a very good chance that one could end up with a very hefty bill to pay and nothing to show for it. Clearly therefore, the only opportunity that presented one with the opportunity to take a legal case was after the ratification of the Convention and it coming into effect in September 2012, at which point the Compliance Committee’s recommendations and findings had been published.

However, despite this ratification of the Convention in June 2012, the ‘access to justice’ provisions in Ireland are still in awful shape, reflecting the reality of a legal system which is a ‘locked Ferrari’.

In case C-240/09[32] Lesoochranárske zoskupenie, relating to a reference for a preliminary ruling from the Supreme Court of the Slovak Republic, a clear message was sent in March 2011 to the national courts regarding their duty to uphold the rule of EU environmental law. Although the European Court determined that Article 9(3) of the Aarhus Convention did not have direct effect in EU legal order, its ‘provisions are intended to ensure effective environmental protection’.  In the words of the Court: “If the effective protection of EU environmental law is not to be undermined, it is inconceivable that Article 9(3) of the Aarhus Convention be interpreted in such a way as to make it practically impossible or excessively difficult to exercise rights conferred by EU law”.

One could also point to Section 8 of the Environment (Miscellaneous Provisions) Act of August 2011:

  • “Judicial notice shall be taken of the Convention on Access to Information, Public Participation in Decision-Making and Access to Justice in Environmental Matters done at Aarhus, Denmark on 25 June 1998”.

The reality is completely different despite the clear direction given above since late 2011. When litigants have actually turned up at the Irish High Court looking for cost arrangements to limit their financial exposure in relation to ‘not prohibitively expensive’, they have been shown the door[33]. In my case when seeking leave as a lay litigant in November 2012, Justice Peart responded in relation to the requirement of the Aarhus Convention and ‘not prohibitively expensive’, that this would be dealt with in January 2013 when the case reconvened, as the European Court’s decision on the Edward’s case was imminent.

This situation requires some explaining in that in November 2010; the Aarhus Convention Compliance Committee found that the cost of access to justice provisions in the UK did not meet the requirements of ‘not prohibitively expensive’ and the UK is now subject to compliance mechanism by UNECE in this regard[34]. This was followed in April 2011 by the European Commission announced that it was referring the UK Government to the European Court of Justice for failing to rectify provisions standing in the way of access to environmental justice in UK law. As a result legal reform is occurring in the UK, although the pace of reform is still slow.

As part of this reform, a test case in relation to ‘not prohibitively expensive’, called Edwards v Environment Agency, was referred by the UK Supreme Court to the European Court for a preliminary ruling on the concept of ‘prohibitively expensive’. The ‘Edwards’ case is a ‘forerunner’ of a more general case that the European Commission is bringing against the UK for failing to ensure costs are not ‘prohibitively expensive’.

When the Edwards case was heard in September 2012 in the European Court in Luxemburg, the Commission intervened in support of the Appellant. Denmark, Greece and Ireland intervened in support of the United Kingdom. In essence, Irish taxpayer’s money was used to fund legal submissions, both written and oral, which had as their aim, the denial of those taxpayers’ legal rights.

While the Advocate General Kokott’s opinion[35] is now published on the case, the actual judgement will not be issued until the morning of the 11th April, the same day as the Judicial Review takes place in the Irish High Court. However, the Advocate General’s opinion does provide some indication of the resulting judgement; see for example points below which she made:

  • Recognition of the public interest in environmental protection is especially important since there may be many cases where the legally protected interests of particular individuals are not affected or are affected only peripherally. However, the environment cannot defend itself before a court, but needs to be represented, for example by active citizens or non-governmental organisations.
  • It would not be compatible with wide access to justice if the considerable risks in terms of cost are, as a rule, liable to prevent proceedings.
  • In examining whether costs of proceedings are prohibitive, account must be taken of the objective and subjective circumstances of the case, with the aim of enabling wide access to justice. The insufficient financial capacity of the claimant may not constitute an obstacle to proceedings. It is necessary always, hence including when determining the costs which can be expected of claimants having capacity to pay, to take due account of the public interest in environmental protection in the case at issue.

Coming back to the reality of the situation, I’ve been given no direction as to what arrangements will be made in relation to ‘not prohibitively expensive’ other that in their action against me the in relation to seeking ‘undue delay’, the State Solicitor is actively seeking their costs and expenses to be awarded against me. So much for respecting the principle of the Convention they ratified and in particular Article 9(5) which states:

  • “In order to further the effectiveness of the provisions of this article, each Party shall ensure that information is provided to the public on access to administrative and judicial review procedures and shall consider the establishment of appropriate assistance mechanisms to remove or reduce financial and other barriers to access to justice”.

Finally in relation to access to justice, the issue of ‘not prohibitively expensive’ is not the only major failure with the Irish legal system. The Convention defines the citizen’s right to challenge the substantive and procedural legality of any decision, act or omission. However, as Professor Aine Ryall of UCC in her 2012 report on access to justice in Ireland for the EU Commission stated[36]:

  • The substance (or merits) of a planning or environmental decision may only be challenged indirectly in judicial review proceedings on the basis that the decision in question is “unreasonable” or “irrational”. “Unreasonable” or “irrational” in this context has been interpreted narrowly by the courts. In order to succeed, the applicant must prove that the decision-maker had no relevant material before it to support its decision or, as one Supreme Court judge famously expressed the test for judicial intervention, whether the contested decision “is fundamentally at variance with reason and common sense”.

On this basis, the Irish courts have tended to defer to the technical expertise of decision-makers such as planning authorities, An Bord Pleanála and the Environmental Protection Agency. Little wonder, that on the Corrib pipeline decision, the developers carried the cost of the €500 million tunnel rather than go to Court with a valid technical argument, which wouldn’t have received a fair hearing.

In other jurisdictions, while the judiciary may not draw such hefty salaries as in Ireland, they are trained in the subject matter of environmental law and the ‘substantive’ issues, such as noise impacts, can be raised in legal proceedings without as in Ireland, the judge solely devolving to the evidence of the regulator.

Fortunately with the upcoming Judicial Review on the renewable energy programme, the evidence on which the case is built relate to failures to complete defined legal procedures on public participation, for which there are findings and recommendations from the UNECE Compliance Committee. If the issue had been one of the ‘substantive’ issues of the National Renewable Energy Action Plan, rather than the ‘procedural’ failings, one wouldn’t have a prayer with regard to the current Irish jurisprudence in the area of environmental law.

8. Conclusions

Not only has seven months of working in the Ukraine before the Orange Revolution in 2004, plus extensive work experience in other places which would not be exactly renown for the behaviour of those in power, attuned me to what those in Western Democracies refer to as somewhat oppressive regimes. However, is there a lot of difference to the Western World? For most people not really, after all here in Ireland and many Western States one can talk about it, read about it, watch it, write about it, even campaign about it, but in reality the decisions are taken behind closed doors without any involvement of the citizen. You have only an appearance of being involved in the decision making, because you are discussing it. There is actually no structure to the decision making and the current decision makers are making very sure you don’t have a ‘look in’.

In a totalitarian state, you just don’t do so much discussing, but for the overwhelming majority life just goes on as usual, same as in the Western World. Then there are those, who are of the somewhat more ‘unreasonable’ disposition, who have other ideas and potentially the means to articulate and progress them. So they are quickly isolated and repressed by the regime, but the regime itself does not ‘take it out’ on the overwhelming majority of the population – it doesn’t have to.

  • In simple terms, democracy means that the people decide.  Political scientists describe our system of voting every few years but otherwise leaving everything up to government as weak democracy.  In weak democracy, citizens have no role, no real part in decision-making between elections[37].

Ireland is a dangerously weak democracy, where power is centralised to the few who sit around the cabinet table and an unaccountable administration dances to their agenda. Any notion that the Irish State exists to serve the welfare of its citizens is laughable. This degree of significant political instability is leading to not only dysfunctional governance, but a massive loss in investment in the country. It is not unsurprising that Ireland has always been associated with a ‘brain drain’; the current flight of the youth of the country being just part of a long standing tradition. The establishment (elite) rules; the youth know that and that there are better opportunities to progress elsewhere, where a system of greater equality and opportunity prevails.

History repeats itself; in 1945 George Orwell published ‘Animal farm’ where the pigs decided everything and the animals had to toil building windmills. So what has changed? The ideology may well be ‘Green’ not red; you may not have to do physical labour building windmills, but you do have to fund them out of your disposal income through increased compulsory charges on your electricity bill. As regards environmental protection, any benefits associated with this renewable energy programme are completely derisible[38]. It may be ‘Green’, but the reality is the Green Moverment is a threat to democracy.

Simply put, the manmade contribution to on-going global warming is not a planetary emergency. However, the bureaucracy has to be kept turning, of which rule number one has always been:

  • “Maintain the problem at all costs! The problem is the basis of power, perks, privileges, and security”.

To this of course must be added that wealth and resources must be diverted to vested support groups and away from those, which are considered political opponents. So the pigs decide; 40% of Ireland’s electricity is to be generated by wind mills controlled by their programme, already their semi-state companies have drawn down €1 billion in loans from the European Investment Bank for infrastructure we don’t need[39] and which will have to be paid for by us through increased electricity charges. Depending on which side of the Atlantic you are on, it is a ‘pork barrel’ or ‘jobs for the boys’.

As with the ‘Borg’ in ‘Star Trek’; ‘Resistance is Futile’. Ordinary people in Ireland, in the midlands in particular where several thousand 185 m high turbines are to be built, are finding that a massive wind energy project is going on around them, for which they have never been informed about nor provided with an opportunity to participate in. This is not in the least bit unsurprising given that neither at National nor County level were the legally required Strategic Environmental Assessments and associated public participations completed for this wind energy programme. Furthermore, the developers simply approached the farmers and signed them up with a confidentiality clause, nobody inform the adjacent neighbours.

The planning approvals will now go straight to An Bord Pleanala as part of the Strategic Environmental Infrastructure Act. This planning authority has never adhered to technical or legal standards and is furthermore characterised by the political decisions of its board, which is composed of political appointees. If you don’t agree with the board’s ‘deliberations’, then you can bring your noise experts, etc, into the High Court – I wish you luck!

Bottom line is; the pigs have decided and the projects are their ‘done deal’

None of this has happened by accident, but rather by apathy of a population, which has ceded the decision making around it to others, who are completely unaccountable. Indeed, the civil servants don’t bat an eyelid in spending considerable amounts of the citizen’s tax money in legal cases to defend their maladministration and prevent the citizen from obtaining their rights, such as with regard to access to simple environmental information in relation to emissions.

Indeed, in relation to my case on the 11th April, it would appear that the State has no intention of respecting a citizen’s right to challenge blatant acts and omissions of their administrative colleagues, in relation to the citizen’s rights to be informed and to participate in the development of this renewable energy programme.  Their office does not serve to ensure proper legal standards in administration, but to protect the power base of that administration and its ‘modus operandi’ of ignoring the legal framework, which applies to it. For that they are paid a health sum of money by you the citizen. There is no doubt that within the metaphor of ‘Animal Farm’, they are the guard dogs of Napoleon the ‘pig’.

In the spring of 2012 I was working in Belgrade and was quite intrigued by one of the posters in a quite striking exhibition on the main street; it said:

  • Dissent protects democracy; Secrecy promotes tyranny.

What an appropriate phrase I thought and sought its origin. It turned out to be part of a quote from Edward Abbey, a rather colourful US author and environmental campaigner. The final part of the quotation is to be found below, at the time I thought it was hyperbole; though one’s viewpoints often can and do change with time:

  • A patriot must always be ready to defend his country against his government”.

Pat Swords BE CEng FIChemE CEnv MIEMA


[1] http://www.unece.org/env/pp/compliance/C2006-17/Response/ECresponseAddl2007.11.21e.doc

[2] Ref. Una Dixon 1st Affidavit 29th Jan 2013

[3] http://www.unece.org/fileadmin/DAM/env/pp/compliance/C2010-54/Findings/ece_mp.pp_c.1_2012_12_eng.pdf

[4] http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:2005:124:0001:0003:EN:PDF

[5] http://www.environ.ie/en/AboutUs/AccesstoInformationontheEnvironment/

[6] http://www.ocei.gov.ie/en/publications/annual-reports/annualreport2011/index.html

[7] http://www.ocei.gov.ie/en/Decisions/

[8] http://www.ocei.gov.ie/en/Decisions/Decisions-of-the-Commissioner/Mr-Gary-Fitzgerald-BL-Department-of-the-Taoiseach.html

[9] http://thestory.ie/2013/02/27/nama-vs-ocei-high-court-judgment/

[10] http://thestory.ie/2013/03/06/nama-vs-ocei-costs-via-twitter/

[11] http://www.ocei.gov.ie/en/Decisions/Decisions-of-the-Commissioner/Mr-Pat-Swords-and-Bord-Plean%C3%A1la.html

[12] See further details: The Committee considers that the provision of “a period of approximately six weeks for the public to inspect the documents and prepare itself for the public inquiry” in order to “to exercise its rights under article 6, paragraph 6”, and provision of “45 days for public participation and for the public to submit comments, information, analyses or opinions relevant to the proposed activity” under article 6, paragraph 7, “in this case meet

the requirements of these provisions in connection with article 6, paragraph 3, of the

Convention”: Section 89(c): http://www.unece.org/fileadmin/DAM/env/pp/mop4/Documents/ece_mp.pp_2011_11_eng.pdf

[13] Affidavit of Una Dioxin Department of Communications, Energy and Natural Resources 7th March 2013.

[14] http://www.unece.org/fileadmin/DAM/env/pp/acig.pdf

[15] http://www.ocei.gov.ie/en/Decisions/Decisions-of-the-Commissioner/Mr-Pat-Swords-Department-of-Communications,-Energy-and-Natural-Resources.html

[16] See Table 1 for a cost of €37 per tonne as opposed to that for €120 per tonne for wind:  http://www.ecofys.com/files/files/serpec_wastesector_report.pdf and http://www.eirgrid.com/media/2004%20wind%20impact%20report%20(for%20updated%202007%20report,%20see%20above).pdf

[17] http://www.merrionstreet.ie/index.php/2011/01/gormley-welcomes-publication-of-environment-miscellaneous-provisions-bill-2011/

[18] http://thestory.ie/2013/03/13/commissioner-decision-on-aie-search-and-retrieval-fees/

[19]http://www.iae.ie/site_media/pressroom/documents/2010/Mar/04/Joint_Oireachtas_Climate_Change_Report_-_March_2010.pdf

[20]http://curia.europa.eu/juris/document/document.jsf?text=&docid=72488&pageIndex=0&doclang=EN&mode=lst&dir=&occ=first&part=1&cid=889485

[21] http://www.bailii.org/ie/cases/IEHC/2006/H243.html

[22]http://courts.ie/Judgments.nsf/09859e7a3f34669680256ef3004a27de/9aeef3e5e1af01d6802578a9003ca326?OpenDocument

[23]http://www.courts.ie/Judgments.nsf/09859e7a3f34669680256ef3004a27de/cf02048062e8f26d802575dd00529598?OpenDocument

[24]http://www.environ.ie/en/DevelopmentandHousing/PlanningDevelopment/Planning/PlanningLegislation-Overview/PlanningActs/

[25]http://www.citizensinformation.ie/en/environment/environmental_law/judicial_review_in_planning_and_environmental_matters.html

[26]http://www.friendsoftheirishenvironment.net/index.php?do=friendswork&action=view&id=858

[27] http://ec.europa.eu/eu_law/eulaw/decisions/dec_20120531.htm#ie

[28] http://ien.ie/2009/report-of-meeting-with-european-commission/

[29] Communication ACCC/C/2008/32: http://www.unece.org/fileadmin/DAM/env/pp/compliance/CC-32/ece.mp.pp.c.1.2011.4.Add.1.e.pdf

[30] http://www.eeb.org/index.cfm/news-events/news/ngos-condemn-anti-democratic-move-by-european-commission/

[31] See page 19 of EU’s 2008 First Implementation Report on Aarhus Convention, where it stated that Article 7 of the Convention on plans and programmes related to the environment would be implemented by Directive 2001/42/EC on Strategic Environmental Assessment:  http://www.unece.org/fileadmin/DAM/env/documents/2008/pp/mop3/ece_mp_pp_ir_2008_EC_e.pdf

[32] http://curia.europa.eu/juris/liste.jsf?language=en&num=c-240/09#

[33] http://www.pila.ie/bulletin/2012/october-2012/3-october-2012/irish-high-court-refuses-application-that-judicial-review-applicant-not-be-exposed-to-prohibitively-high-costs/ and http://www.pila.ie/bulletin/2012/november-2012/28-november-2012/irish-high-court-refuses-to-make-a-protective-costs-order-in-an-environmental-case/

[34]http://www.unece.org/fileadmin/DAM/env/pp/mop4/Documents/ece_mp_pp_2011_L_20_e.pdf

[35] http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=CELEX:62011CC0260:EN:HTML

[36] http://ec.europa.eu/environment/aarhus/access_studies.htm

[37] http://www.citizenshandbook.org/

[38] If global temperatures are rising, which they aren’t, then the benefits can only be quantified as about €5 million per annum, which is a sad reflection of €30 billion in capital expenditure, for which the bulk of the infrastructure will be life expired in 15 years: Bishop Hill

[39] See for instance Chapters 8 and 9:                        http://www.iae.ie/site_media/pressroom/documents/2011/Apr/06/IAE_Energy_Report_Web2_05.04.2011.pdf

Mar
31

Stall In Rising Temperatures Leaves Alarmists Puzzled

Twenty-year hiatus in rising temperatures has climate scientists puzzled

Climate change

The fact that global surface temperatures have not followed the expected global warming pattern is now widely accepted. Picture: Ray Strange Source: The Australian

DEBATE about the reality of a two-decade pause in global warming and what it means has made its way from the sceptical fringe to the mainstream.

In a lengthy article this week, The Economist magazine said if climate scientists were credit-rating agencies, then climate sensitivity – the way climate reacts to changes in carbon-dioxide levels – would be on negative watch but not yet downgraded.

Another paper published by leading climate scientist James Hansen, the head of NASA’s Goddard Institute for Space Studies, says the lower than expected temperature rise between 2000 and the present could be explained by increased emissions from burning coal.

For Hansen the pause is a fact, but it’s good news that probably won’t last.

International Panel on Climate Change chairman Rajendra Pachauri recently told The Weekend Australian the hiatus would have to last 30 to 40 years “at least” to break the long-term warming trend.

But the fact that global surface temperatures have not followed the expected global warming pattern is now widely accepted.

Research by Ed Hawkins of University of Reading shows surface temperatures since 2005 are already at the low end of the range projections derived from 20 climate models and if they remain flat, they will fall outside the models’ range within a few years.

“The global temperature standstill shows that climate models are diverging from observations,” says David Whitehouse of the Global Warming Policy Foundation.

“If we have not passed it already, we are on the threshold of global observations becoming incompatible with the consensus theory of climate change,” he says.

Whitehouse argues that whatever has happened to make temperatures remain constant requires an explanation because the pause in temperature rise has occurred despite a sharp increase in global carbon emissions.

The Economist says the world has added roughly 100 billion tonnes of carbon to the atmosphere between 2000 and 2010, about one-quarter of all the carbon dioxide put there by humans since 1750. This mismatch between rising greenhouse gas emissions and not-rising temperatures is among the biggest puzzles in climate science just now, The Economist article says.

“But it does not mean global warming is a delusion.”

The fact is temperatures between 2000 and 2010 are still almost 1C above their level in the first decade of the 20th century.

“The mismatch might mean that for some unexplained reason there has been a temporary lag between more carbon dioxide and higher temperatures in 2000-2010.

“Or it might mean that the 1990s, when temperatures were rising fast, was the anomalous period.”

The magazine explores a range of possible explanations including higher emissions of sulphur dioxide, the little understood impact of clouds and the circulation of heat into the deep ocean.

But it also points to an increasing body of research that suggests it may be that climate is responding to higher concentrations of atmospheric carbon dioxide in ways that had not been properly understood before.

“This possibility, if true, could have profound significance both for climate science and for environmental and social policy,” the article says.

There are now a number of studies that predict future temperature rises as a result of man-made carbon dioxide emissions at well below the IPCC best estimate of about 3C over the century.

The upcoming IPCC report is expected to lift the maximum possible temperature increase to 6C.

The Research Council of Norway says in a non-peer-reviewed paper that the best estimate concludes there is a 90 per cent probability that doubling CO2 emissions will increase temperatures by only 1.2C to 2.9C, the most likely figure being 1.9C.

Another study based on the way the climate behaved about 20,000 years ago has given a best guess of 2.3C.

Other forecasts, accepted for publication, have reanalysed work cited by the IPCC but taken account of more recent temperature data and given a figure of between 1C and 3C.

The Economist says understanding which estimate is true is vital to getting the best response.

“If as conventional wisdom has it, global temperatures could rise by 3C or more in response to a doubling of emissions, then the correct response would be the one to which most of the world pays lip service; rein in the warming and the greenhouse gases causing it,” the article says.

“If, however, temperatures are likely to rise by only 2 degrees Celsius in response to a doubling of carbon emissions (and if the likelihood of a 6 degrees Celsius is trivial) the calculation might change,” it says.

“Perhaps the world should seek to adjust to (rather than stop) the greenhouse-gas splurge.

“There is no point buying earthquake insurance if you don’t live in an earthquake zone.”

According to The Economist, “given the hiatus in warming and all the new evidence, a small reduction in estimates of climate sensitivity would seem to be justified.” On face value, Hansen agrees the slowdown in global temperature rises can be seen as “good news”.

But he is not ready to recalculate the Faustian bargain that weighs the future cost to humanity of continued carbon dioxide emissions.

Hansen argues that the impact of human carbon dioxide emissions has been masked by the sharp increase in coal use, primarily in China and India.

Increased particulate and nitrogen pollution has worked in the opposite direction of rising carbon dioxide levels in the atmosphere.

Another paper published in Geophysical Research Letters on research from the University of Colorado Boulder found small volcanoes, not more coal power stations in China, were responsible for the slowdown in global warming.

But this did not mean that climate change was not a problem.

“Emissions from volcanic gases go up and down, helping to cool or heat the planet, while greenhouse gases from human activity just continue to go up,” author Ryan Neely says.

Hansen’s bottom line is that increased short-term masking of greenhouse gas warming by fossil fuel particulate and nitrogen pollution represents a “doubling down” of the Faustian bargain, an increase in the stakes.

“The more we allow the Faustian debt to build, the more unmanageable the eventual consequences will be,” he says.

Mar
23

Can Wind Turbines Cause Developmental Deformities In Horses?

The following is the summary of a case study of a group of Lusitano horses that have been monitoried over 4 years which were the subject of a masters thesis at the Faculty of Veterinary Medicine, Technical University, Lisbon completed in 2012.

The study was performed by Teresa Margarida Pereira Costa e Curto,  ADVISOR: Dr. Maria da Conceição da Cunha and Vasconcelos Peleteiro CO-ADVISOR: Dr. Maria Luisa Jorge Mendes

The study reports the findings from a stud where 11 foals developed flexural deformities of the front limbs, after they were born. (Acquired flexural deformity of the distal interphalangeal joint).

In this stud farm, the owner has been breeding normal and physically sound horses since 2000. There were no changes in diet, exercise or any other significant alteration in management. Until in 2008, wind turbines were installed adjacent to the property and grazing paddocks.
Since this date, a good number of foals and yearlings have developed deformities.

The subjects of the study were:
-11 Lusitano horses. Age between 0 and 48 months old.
-6 males and 5 females
-9 were born at the stud farm,  2 were acquired from a different breeder.

The above image shows the same foal at 3 and 6 months of age


A foal was bought from another breeder to exclude a possible genetic link to this problem. He came to the farm at 15 days old and like the others, developed a flexural deformity.

Radiological examination of front limbs

The following tests were used for the study:
• Anamnesis
• Clinical examination
• Goniometry
• Ultrasound and x-ray
• Measurement of cortical bone
• CT
• Desmotomy of the check ligament
• Histopathology
• Sound measurements
• Measurements of Ground vibration

Proximity of Horses to Wind Turbines

Aerial View of Farm Proximity To Wind Turbines

Measurements of ground vibration were made at different distances from the wind turbines, with the same equipment that is used to detect seismic vibrations (earthquakes). The results of these measurements, showed ground vibration at different frequencies.
Research has shown that vibration effects bone metabolism.

Cellular Mechanotransduction is the mechanism by which cells convert mechanical signals into biochemical responses. Based on the mechanical effects on cells it was proposed in this research project that the ground vibrations were responsible for a increased bone growth which was not accompanied by the muscle-tendon unit growth leading to the development of these flexural deformities.

Note

The above research project was based solely on this case study. Therefore, further research is necessary in order to validate these preliminary findings and hypothesis. Regarding the sound that the wind turbines produce, measurements were taken and studies have demonstrated some cellular damage is caused by low frequency noise.

RESEARCH TITLE:             Acquired flexural deformity of the distal interphalangic joint in foals

ABSTRACT
Since 2008, a high prevalence of front limb acquired flexural deformities was observed in a Lusitano stud farm. This work aims to evaluate this problem by reporting the results from tissue alterations in the affected animals as well as environmental conditions and management changes, which could have led to this observation. A total of eleven affected animals were studied. In these, a complete physical and orthopaedic examination were performed specifically the determination of the angle between the dorsal hoof wall and the floor. Radiographic examination, CT imaging, determination of the thickness of the cortical bone of the third metacarpian and histopathology of some tissues collected in biopsy and necropsy were done in a subset of affected foals.

All the animals had been supplemented with balanced commercial diet for equine. To investigate a possible genetic cause, two foals from distinct bloodlines were brought to the stud. These also developed the deformities after 6 months. Two of the affected foals were placed in a
pasture away from the initial one and two others were admitted at the Faculty of Veterinary Medicine of Lisbon. In those animals, except for one that had to be euthanized for humane reasons, an improvement was observed on their condition, with partial recovery of the deformity.
Histopathology was performed from (i) the tendon obtained by surgical desmotomy in one foal, (ii) tendon biopsies were performed in three foals and (iii) from the tissue of one foal during necropsy. Histologically the most significant alterations were the dissociation of myofibrils of the smooth muscle. This was predominantly seen in the small intestine but also in the walls of small capillary vessels, including those of the tendon vasculature. The flexural deformities have a complex and multifactorial etiopathogeny. They occur due to uncoupling of the longitudinal development of the bone and its adjacent soft tissues, but also from shortening of the tendon-muscle unit in response to pain.
In the case series presented here, there was no obvious cause for the development of this problem, therefore we hypothesised that unusual environmental conditions might have played an important role in the development of this condition, especially those introduced in recent years.

The Full Thesis can be downloaded here in Portuguese.

Mar
19

Update On The Legal Challenge From Pat Swords

By Pat Swords Turn 180

Originally Posted On Bishop Hill

On Tuesday 12th of March the case scheduled to be heard the next day (13th) went instead into adjournment until the 11th April. There are complex legal issues involved in the case, which I have not yet had the time to finish writing up, but they go beyond the renewable energy issues to the core principle of access to justice and ‘who watches the watch keeper’. The lawyers on both sides have agreed to extra time to prepare additional written affidavits. In summary though, due to Ireland’s failure to ratify the Convention, I could not have taken my case in the Court until after Ireland’s ratification of the UNECE Convention took effect in September 2012. As it turned out, the ruling had by then come through from the UNECE Compliance Committee and I brought it before the High Court and got leave in early November 2012, within the recognised time frame applying post ratification.

The State’s position is that the National Renewable Energy Action Plan was notified to the EU Commission on the 30th June 2010 and as it was not then taken into Judicial Review, they have full legitimacy to continue to implement. The detail is not straightforward; the State is doing everything it can to shut out the citizen from challenging it in the Courts; there is no democracy only diktat and they intent to keep it that way. On my side I’m bringing in a UN ruling, which the State is refusing to recognise, even though it both signed and then finally ratified the UNECE Convention. My ‘defense’ in relation to not being able to bring a Judicial review until after ratification is fully valid but unique, as such circumstances have never happened before. Potentially the case could in time be referred to the European Court, as it is the Judge is being requested to face down the State administration, create precedence and finally open the door for access to justice procedures, which have to date been denied to citizens here.

Continue Reading Here

Mar
18

Operation of Wind Turbines and Legal Liability

Operation of Wind Turbines and Legal Liability

By: Pat Swords Turn 180

1.0 General

The EU’s and Ireland’s rush to renewable energy has created a very generous investment climate for those engaged in this sector. Many landowners would therefore be tempted to consider the construction of wind turbines on their land in order to participate in financial windfall. However, just like in Roman times, ‘Caveat Emptor’ applies, i.e. let the buyer beware.

There are very significant legal liabilities associated with the operation of such large and obtrusive wind turbines, which have been ignored to date, but will increasingly come to fore, as the general public starts to increasingly question this technology and the excessive costs and environmental impacts associated with it.

In this regard, two main considerations apply. Firstly in implementing these renewable programmes at such a rapid pace, the authorities have by-passed the legally binding procedures related to environmental assessment and democratic accountability. As the recent legal ruling from the United Nations Economic Commission for Europe (UNECE) has demonstrated, major failings have occurred in relation to the obligations under the Aarhus Convention on Access to Information, Public Participation in Decision-Making and Access to Justice in Environmental Matters, which is a binding component of EU and Member State law.

With regard to the implementation of the renewable energy programme, the EU is now required to put in place the necessary measures, such that they ensure that the arrangements for public participation in a Member State are transparent and fair and that within those arrangements the necessary information is provided to the public. In addition, such a legislative framework must ensure that the requirements of the Convention are met, in relation to reasonable time-frames, allowing for sufficient time for informing the public and for the public to prepare and participate effectively, allowing for early public participation when all options are open, and ensuring that due account is taken of the outcome of the public participation.

While this effectively demonstrates the planning approvals and funding arrangements for renewable energy projects to date have been implemented without ‘proper authority’, and hence are open to legal challenge[1], there are further implications related to the failures to complete the necessary environmental assessments. Since 2004 both EU and Irish legislation required that a programme, which led to the development consent of wind farms, should have been subject to Strategic Environmental Assessment. This required the preparation of a detailed Environmental Report, followed by an in-depth public consultation. This was by-passed, a situation which also occurred in other Member States. Therefore in Ireland, no such Environmental Report exists.

This has significance; the Environmental Report should have addressed the effects of the renewable energy programme on biodiversity, population, human health, fauna, flora, etc. It should also have addressed the measures envisaged to prevent, reduce and as fully as possible offset any significant adverse effects on the environment of implementing the programme. Member States should have monitored the significant environmental effects of the implementation of the programme in order to identify at an early stage unforeseen adverse effects, and to be able to undertake appropriate remedial action.

Not only did none of this happen, but at the individual project approval stage, European law is clear in that the planning authority cannot simply rely on the developer’s documentation, such as his Environmental Impact Statement. The 1985 Directive on Environmental Impact Assessment, which regulates all significant projects, including wind farms, is very specific in Article 3 of this Directive, that the competent environmental authority must undertake both an investigation and an analysis to reach as complete an assessment as possible of the direct and indirect effects of the project concerned on the factors:

(a)  Human beings, fauna and flora;

(b)  Soil, water, air, climate and the landscape;

(c)  Material assets and the cultural heritage;

(d)  The interaction between the factors referred to in points (a), (b) and (c).

However, Ireland failed to transpose and implement this measure. As the European Court of Justice stated in its March 2011 ruling in case C-50/09 against Ireland; the competent authority may not confine itself to identifying and describing a project’s direct and indirect effects on certain factors, but must also assess them in an appropriate manner, in the light of each individual case. While Ireland’s failure to comply with this ruling has now lead to the situation where the European Commission is calling for it to be fined, there are other implications. Namely countless wind farms have been approved throughout the country, where both at the national level and at the individual project level, there has been a complete failure to assess properly the environmental impacts associated with these turbines and ensure that the necessary mitigation measures are in place.

2.0 Environmental Impacts

Wind turbines have a very significant visual impact, while there is also a significant noise impact and a significant impact on bird and bat populations. The noise impact occurs from two sources, that inherent in the rotation of the gears and bearings of the turbine and secondly in relation to the ‘swoosh’ of the turbine blades as they pass the support column of the turbine. The second feature is a unique very low frequency sound, which is called infra-sound. Until the widespread roll out of wind turbines, such infra-sound impacts would not have occurred in normal circumstances. Furthermore, as the necessary environmental impact assessments and associated monitoring were not completed for the renewable energy programme, this infra-sound noise impact was not properly assessed and regulated before the wind energy programme was implemented.

As a result there is increasing evidence of noise complaints related to wind turbines with associated reports of ill health. This is confirmed by recent scientific literature, such as an in-depth independent study of a proposed wind farm in Holland[2], which pointed out:

“Low frequency sound is particularly annoying, when it occurs alone or with low levels of sound at higher frequencies. This means that it is usually more annoying indoors than outdoors, since the high frequencies are more attenuated by the sound insulation of the house than the low frequencies are. Also it is often more annoying in the evening and at night, when it is otherwise quiet”.

“Prolonged exposure to audible low frequency sound may cause fatigue, headache, impaired concentration, sleep disturbance and physiological stress”.

Indeed, conventional methods of assessment and regulation of noise impacts have not proved suitable in relation to the infra-sound associated with wind turbines.

Similar failings have occurred in relation to biodiversity, particularly birds and bats. While turbines may appear to be moving slowly, due to the sheer size of the blades, the tip velocities are extremely high, 80 m/s (nearly 300 km/h) is not uncommon. This is of course lethal to any birds or bats, which get caught by the blades, to which must also be added the disturbed air patterns in the vicinity of the blades, which cause loss of flight control and ability to avoid the hazard.

In this regard it is interesting to consider the ‘advice’ given by the EU’s Intelligent Energy Europe’s Good Practice Wind (GP Wind) programme[3], which is designed to speed up the permitting procedures for wind energy.

“Effectively protecting terrestrial birds requires early planning and mapping (if necessary combined with a Strategic Environmental Assessment) to avoid destroying their habitats, nesting zones and feeding areas, or disturbing their migration routes. Clear and high quality Environmental Impact Assessment (EIA) standards are necessary to ensure that all relevant impacts are studied in the EIA, especially for habitats and species identified in the Habitats Directive. Adopting a mitigating hierarchy can help to prioritise the necessary steps”.

As mentioned before, this simply hasn’t happened to date in Ireland.

3.0 The Principle of Nuisance

In the 1860s in Lancashire John Rylands constructed a reservoir on land he was renting to supply water to his steam-powered textile mill. Thomas Fletcher operated mines on nearby land and had tunnelled up to old disused mines, which were under the land where Rylands’ reservoir was located. The reservoir started to fill and water entered the mine and flooded it, so Fletcher sued Rylands resulting in the landmark case Rylands v Fletcher, which went as far as the British House of Lords. The application and interpretation of the Rylands rule has been an important step in the development of legal policy in the British based legal system relating to modern industry, risk allocation, liability and negligence.

In layman’s terms, if you bring something onto your land, which then has a detrimental impact on a neighbour’s land, then there is liability. In the 1985 legal case of Hanrahan versus Merck, Sharpe and Dohme, in relation to the alleged impact of their pharmaceutical plant on his dairy farm near Carrick on Suir, the appeal process used this Victorian case law as criteria for concluding that Merck had caused a ‘nuisance’ to the nearby farm. While there was no scientific evidence of pollution, the company had been responsible for a number of odour incidences in the surrounding area. As a result, Hanrahan won a compensation settlement of 800,000 Irish Pounds.

In many respects, what this case demonstrated was the lack of proper structures and legislation in Ireland to deal with the necessary coexistence between industry and the surrounding environment. At the same time as Ireland now saw fit to modernise these measures, the comprehensive European Union legislation on the environment was also evolving. As a result the Environmental Protection Agency was established by an Act of the Oireachtas in 1992. Section 108 of this Act defines in relation to noise as a nuisance[4]:

“Where any noise which is so loud, so continuous, so repeated, of such duration or pitch or occurring at such times as to give reasonable cause for annoyance to a person in any premises in the neighbourhood or to a person lawfully using any public place, a local authority, the Agency or any such person may complain to the District Court and the Court may order the person or body making, causing or responsible for the noise to take the measures necessary to reduce the noise to a specified level or to take specified measures for the prevention or limitation of the noise and the person or body concerned shall comply with such order”.

While the same legislation recognises that “it is a good defence” to be in compliance with recognised technical standards, or even regulations issued by the authorities, if it is demonstrated in the Court that nuisance is occurring, then the Court has the power to ensure that the noise emissions are brought to a level, which no longer creates nuisance. Note: This could entail that the wind farm has to cease operation. It is also important to note that as a wind turbine ages, its efficiency drops and its noise output increases.

3.0 Environmental Liabilities

When the Maastricht Treaty was passed in 1992, it stated that Community policy on the environment “shall be based on the precautionary principle and on the principles that preventive action should be taken, that environmental damage should as a priority be rectified at source and that the polluter should pay”. While this is a simple concept, it took until 2004 before the necessary legislative measures were finalised with the Directive on environmental liability with regard to prevention and remedying of environmental damage (2004/35/EC).

The fundamental principle of this Directive is that an operator whose activity has caused the environmental damage or the imminent threat of such damage will be held financially liable, in order to induce operators to adopt measures and develop practices to minimise the risks of environmental damage, so that their exposure to financial liabilities is reduced. An operator can be anything from a sole trader, such as a farmer, to a full multinational. In German alone it is estimated that some four million companies are affected by this legislation.

The Directive also impacts on the citizen, in that it contains provisions in relation to the rights of those affected by the environmental damage or Non-Governmental Organisations (NGOs), to submit their observations to the competent authority and their request for action under the terms of the Directive. Where it is shown in a plausible manner that environmental damage exists, the competent authority is required to consider any such observations and requests for action. Then, as soon as possible, the competent authority is required to accede to or refuse the request for action and shall provide the reasons for it. In this regard the citizen has the right of access to a court or other independent and impartial public body competent to review the procedural and substantive legality of the decisions, acts or failure to act of the competent authority. Indeed, these measures can be seen on the website of the Irish Environmental Protection Agency[5].

Where there is an imminent threat of environmental damage, the competent authority is empowered to require the operator (the potential polluter) to take the necessary preventive measures, or will take such measures itself and recover the costs incurred at a later date.  Where environmental damage has occurred, the competent authority is empowered to require the operator concerned to take the necessary restorative measures or will take such measures itself and recover the costs incurred at a later date.

The scope of the Directive applies in relation to wind farms and any damage to protected species and natural habitats, where ‘damage’ means a measurable adverse change in a natural resource or measurable impairment of a natural resource service which may occur directly or indirectly.

An example of this is actually provided in the Environmental Protection Agency guidance on implementing the environmental liability regulations, for the case of a wind farm, where the peat displaced in the construction caused environmental damage to a salmonid river[6]. Clearly if a wind farm is considered by a person affected by its activities or by an NGO engaged in environmental protection to be causing damage to protected species or natural habitats, then they can request the Environmental Protection Agency to investigate the issue. If damage is determined to be occurring, then the wind farm operator is liable and is required to implement the necessary environmental remediation.

4.0 Conclusion

It is highly unfortunate that in the completely unjustified rush to implement a policy of some 7,145 MW of wind energy in the Irish Republic[7], amounting to some four thousand turbines, the legally binding procedures related to environmental assessment and democratic accountability have been by-passed. However, it is clearly evident that adverse environmental impacts are occurring in relation to wind farm developments. While there are legal implications in relation to financial damages in respect of the authorities, who approved without ‘proper authority’ this renewable programme, there are also serious legal implications in relation to those who operate such facilities and cause such environmental impacts. Furthermore, the aggrieved citizen is not dependent on the authorities to enforce such measures, there are existing means of legal recourse available, which will become more readily available, as Irish legal procedures have to adapt to the UNECE Aarhus Convention’s requirements of fair, equitable, timely and not prohibitively expensive.

Pat Swords, BE CEng FIChemE CEnv MIEMA


[1] See following link for the details related to the illegalities of the renewable energy programme: http://www.turn180.ie/?p=609

[2] http://vbn.aau.dk/files/62413823/Maastricht_Moeller_et_al_2011.pdf

[3] http://www.project-gpwind.eu/index.php?option=com_content&view=article&id=42&Itemid=225

[4] http://www.irishstatutebook.ie/1992/en/act/pub/0007/sec0108.html#sec108

[5] http://www.epa.ie/whatwedo/enforce/liab/

[6] See Case Study 2: http://www.epa.ie/downloads/advice/general/Liability_Regulations%20Final%20August%202011.pdf

[7] National Renewable Energy Action Plan (NREAP)

Mar
14

Hitting the “Jobs From Wind Turbines” On The Head

The following is a letter published in the Irish Times written by John Rogers, Rathowen, Co. Westmeath

A lot of the debate regarding the proposal to install more than 2,500 wind turbines in the Midlands. is ill-informed, speculative, or plain wrong.

The proposed turbines are 185 m high, the chimney at Kinnegad cement factory is 125 m and although not moving, is visible from 30 km away. Fact. Imagine what the Midlands with 2,666 turbines, with three blades apiece, will appear like.

Approximately 1,000 landowners would have these machines installed on their lands, hoping to get €18,000 for each unit annually. This represents a significant sum of money in these difficult times and cannot be ignored. What is being overlooked is that each unit takes 2.5 hectares of land out of production if access roads, etc are considered. Calculate the loss of area aid and possible other EU payments and this looks less attractive. Then the tax man will most certainly want his share. These figures are possible to calculate, less easy is the price of friendship and value of neighbours. Will people next to these turbines be willing to help with a cow calving or worry about a strange van on the road? Possibly not.

There are 20,000 jobs in the pipeline according to the politicians and the promoters and they are correct. The only trouble is the pipeline has its outlet in Denmark, Germany and China. Yes there will be jobs here on site: hands up who has the skills and qualifications necessary to erect these giants? The locals will get jobs: those big cranes will need flagmen and women to stop the traffic, and more to pour a bit of cement. When the turbines are up and running they will be operated remotely, possibly by the power user in the UK, so don’t rely on anything being needed here. There may be need for extra gardai, keeping warring neighbours apart, and medical staff to deal with the stress-related complaints caused by the noise and other pollution. Even these jobs are doubtful as we don’t have the money to pay them.

One ray of sunshine is that the local property tax band that you are in will be reduced substantially. If you are within several miles of one of these machines you are certainly in the €0-100,000 band, and nearer to the zero than the top.

These wind farms will be owned by foreign investors, erected using foreign equipment and staff, operated by a handful of permanent employees, the product sold to the UK, which will get the benefit of the carbon credits, power and not have to worry about the environmental impact. The benefit to this country will be so small in comparison to the reward that it is laughable that we are considering it at all.

Mar
12

Science Under Assault

John Droz Jr.

Science Under Assault

Mar
12

10 Ways To Tackle A Wind Turbine

Ten Ways to Kill Big Wind

How a Little Island Stopped a Huge Industrial Wind Project

Simulated View of Wind Turbines on Molokai
Simulated View of Wind Turbines on Molokai

Despite many victories, communities around the world are still facing a plague of industrial wind projects that like hideous War of the Worlds steel monsters are destroying communities, mountains, and wildlands, slaughtering birds and bats, sickening people and driving them from their homes.

Even though these wind projects do not reduce greenhouse gases or fossil fuel use, they have dreadful environmental, social and economic impacts on whole regions. But they are a tool for energy companies and investment banks to make billions in taxpayer subsidies that get added to our national debt.

The good news is that communities worldwide are learning how to defeat these dreadful projects. More and more laws and moratoriums are being passed against them, while other projects are defeated on legal grounds or by overwhelming public opposition.

In Hawaii, an industrial wind project that would have constructed ninety 42-story turbine towers across seventeen square miles of Molokai has been defeated by a determined two-year effort of the island’s residents. In the process we learned many tactics, which I’ve tried to summarize below and are further described in Saving Paradise:

  1. Show wind projects for what they are: industrial. Not environmental, not green, not renewable, and cause no reductions in greenhouse gases or fossil fuel use, no long-term jobs and few short-term ones.
  2. Don’t be nice. These wind developers are your enemies: they want to destroy where you live, steal your money (property values), and are quite happy to literally drive you from your homes. Some may lie, cheat, bribe, buy politicians, and do whatever else they can to win. They won’t be fair and you can’t trust them.
  3. Create a group and get your community behind you. Point out property value loss, human health issues, environmental destruction, tourism impacts, and all the other dreadful results of industrial wind. If you have a homeowners’ associations, make them aware of the danger so they can join the fight.
  4. Publicize your case. In the newspapers, TV and radio, on blogs and in nationwide petitions. Use videos and  good graphics. Go viral, worldwide. Develop a good professional website with lots of information and ways for viewers to participate. Community members should write op-eds and letters to the editor. A very powerful tool is frequent press releases that pass on news reports from National Wind WatchIndustrial Wind Action Group and other organizations about the devastating impacts of industrial wind. These press releases should be sent to all relevant media outlets and local, state and national legislators.
  5. Do mailings to everyone. In Molokai we sent two mailings to all the island’s 2,700 addresses. The first mailer described the dangers of the project and included a survey with a stamped return envelope. We had a massive response, with 97% of responses against the project, and our group gained hundreds of new members. A year later we sent a second mailer with photo mockups showing how the turbines would tower over homes and landscapes. This mailer also included a bumper sticker which many residents then put on their cars.
  6. Be visible. Put up lots of signs, both homemade and professionally done. Put up billboards if you can. Professional signs show you mean business, and are taken more seriously.
  7. Find legislators who will help you. On the state level, Republicans are often more responsive and more concerned about the environment than traditionalist Democrats who have bought the idea that wind is environmental (or who are receiving contributions from wind companies).
  8. Litigate. Find every avenue to impair or slow the wind developers. Once the Washington industrial welfare subsidies are removed, industrial wind companies will vanish overnight.
  9. Get property value loss appraisals. Average losses of 40% or more are being reported; in Molokai, one of the reasons the landowner planning the project cancelled it was they estimated a 75% property value loss on their lands near the project. Publicize the loss of assessed value at county level, and how that will reduce tax revenues. In most cases, property value loss far exceeds any revenue the county might receive from the project.
  10. Civil disobedience. Politicians and energy companies are terrified of this. Don’t be afraid to go to jail to protect the land and homes you love. On Molokai we planned if necessary to start a hunger strike on the island, and there were people ready to starve to death to protect our island. The level of your commitment is equal to the level of your success

Bestselling author, advisor to the US and foreign governments, human rights and war correspondent, award-winning poet and international energy expert, Mike Bond has lived and worked in over thirty countries on six continents. His works have been translated into many languages and have been praised by critics on both sides of the Atlantic for their intricate plots, fascinating characters, extraordinary settings, and explosive pace.

    Mar
    01

    Ireland’s Unethical Environmental Policies

    The Conclusion of a letter to the EU Ombudsman.

    By Mark Duchamp, Executive Director
    European Platform against Windfarms (EPAW)

    Government policy on renewable energy is finalised before any public participation is allowed. No SEA is performed, and objectives (“targets”) are drawn from a hat (“20-20-20”). When the public is invited to participate, it is not provided with meaningful information (such as SEAs or an analysis of alternative investments), it is not given enough time to submit its comments, and these are made in vain as the decisions are already made.

    Windfarm projects are being approved on the basis of NREAP that were imposed arbitrarily on the people in complete disregard for EU legislation transposing the Aarhus Convention, and for Directive 2001/42/EC on SEAs.
    The only recourse citizens have is a justice system which notoriously fails to even approach the minimum requirements in relation to access to justice7.
    Where is the data and the assessments of the alleged benefits for environmental protection, which are supposed to justify these pharaonic financial and environmental costs? The Irish Administration doesn’t have them; the EU Commission doesn’t have them either. Yet there is a programme in place being used to approve and fund countless environmentally damaging projects under this ‘renewable banner’, so how on earth can this be transparent and in compliance with the Aarhus Convention?
    The EU supposedly evolved from the resolution that populism would no longer dominate the governance of the European continent. Allegedly, as is stated in Article 2 of the Treaty on European Union:

    “The Union is founded on the values of respect for human dignity, freedom, democracy, equality, the rule of law and respect for human rights, including the rights of persons belonging to minorities. These values are common to the Member States in a society in which pluralism, non-discrimination, tolerance, justice, solidarity and equality between women and men prevail”.

    The reality is much different: the European Commission has been forcing a programme upon its citizens from the top down, at a cost of billions of Euros to consumers and taxpayers, not to mention immensely negative environmental and economic impacts, with nothing but populist statements to justify it. As regards the specific situation in Ireland, the failures in relation to compliance with the rule of law have been well documented in CHAP (2010) 046 Complaint Case to the European Commission, in the EU Ombudsman Complaint 2587/2009/JF, in the Aarhus Convention Compliance Committee Communication ACCC/C/2010/54, in this EU Ombudsman Complaint 1892/2012/VL, and more recently in the documentation submitted to the Irish High Court on Judicial Review 2012/920JR. So the question is: when is something going to be done to demonstrate that Article 2 of the Treaty on the European Union is a reality and not a myth?

    Mar
    01

    Assessing the Climate Change Issue

    David Whitehead Turn 180

    As a starting point here are a small number of propositions which I think are axiomatic:-

    FIRST The Global Climate System is subject to multiple, interacting, only partially understood, human and non-human influences,

    SECOND Our ability to foresee the future evolution of the Global climate is quite limited,

    THIRD certainty is not in prospect any time soon.

    FOURTH Stabilising the concentration of CO2 in the atmosphere holds no prospect of stopping climate change.

    FIFTH In all human activity the main cause of Problems is Solutions.

    Clearly from an intellectual perspective “ Ciimate Change”, CC/CAGW is a “Wicked Problem” . It lacks anything that might be considered to be a “Solution”. Human actions might mitigate or exacerbate the “problem”, we can do better or worse, but we cannot “solve “ the “problem” – not least because there is little understanding and/or agreement as to what the “problem” actually is.

    This is at least partly because the spectrum of debate about the Global Climate is such that we can find scientists who are adamant that they can predict the long term future of the Global Climate with accuracy and precision but unfortunately this group includes scientists making predictions that are incompatible with each other. There are also scientists who conclude that making predictions of the future state of the Global Climate with precision and accuracy is beyond our ability.

    The uncertainty about the climate future cannot therefore be resolved on any timescale required of Political Decision Makers because Climate Science can not reliably tell them what to do or even if they have to do anything. In the context of the DO NOTHING option it should be noted that the carbon intensity of WORLD Gross Economic Product peaked in or around 1920 and in 2006 it had declined to the level of ( almost pre industrial) 1870. The cost of energy is such that there is clear economic incentive to minimise its intensity of use.

    As a result of the large distribution of scientific ( and pseudo scientific) perspective it is very easy for advocates of differing persuasion to pick and choose courses of action based on political or ideological convenience and allows them latitude to urge their position on largely illiterate or ignorant ( scientifically) politicians and their political constituencies. There are also a number of factors that mitigate against rational, as opposed to ideologically driven debate.

    (A) There is clearly a bias against ADAPTATION to climate change – despite historically conclusive demonstration hat this strategy has been successfully pursued by mankind for millennia.

    (B) Climate science has become heavily politicised to the extent that the scientific validity of both data and conclusions is now questionable and questioned

    (C) There has been systematic misrepresentation of a connection between disasters and CC/CAGW.

    (D) Playing Politics through science has become stock in trade for research institutions, politicians and policy advocates of various leanings,

    (E) Issue advocacy has been applied by constituencies such as IPCC, WWF, The Green Parties, opportunist businessmen and journalists to reduce the scope of options available to decision makers .

    Theory posits that decisions should not rely on specific projections about how events will turn out, and decision makers should not rely on predictions as a basis for decision making unless ALL the following criteria are met:-

    The Predictive Skill of the forecaster is known

    The decision makers have experience in understanding and using predictions,

    The time lapse between the prediction and the predicted event(s) is short,

    There are few, if any, alternatives to the prediction on which the decision is to be based,

    The outcomes of various courses of action are understood in terms of well constrained uncertainties.

    All long term Global Climate predictions ( or projections) fail with respect to these criteria irrespective of whether they are expressed as forecasts or probabilistic scenarios. Consequently any decisions relying on such predictions are bound to be intrinsically unsound. (A decision to salt roads in the face of an overnight weather forecast would meet the criteria).

    A related, but separate issue arises because CC/CAGW mitigation Policy Advocates have persuaded decision makers in many countries that the atmospheric concentration of CO2 is increasing wholly or significantly because of the combustion of fossil fuel, that the increase can be halted or mitigated by political action in developed economies, that doing so will constrain or halt the predicted CC/CAGW and that this can be accomplished by the use of existing technology and without serious economic or social hardship.

    Nobody knows how to “decarbonise” a significant sized economy, MUCH LESS THE WORLD ECONOMY, using existing technology on the timescale implied by the Emissions Reductions Targets adopted ( in some cases , including that of Ireland IMPOSED). The idea that there is an economically benign technological “fix” is irresistible to political decision makers and the inducements which have to be put on offer because the wind, wave and solar generating technologies are very expensive (and not particularly effective in terms of CO2 emission mitigation), are financially irresistible to rent seeking businessmen.

    The well known criteria for a Technological fix are :-

    [1] The Technology must embody a direct cause/ effect relationship which is probably not met by the existing technologies.

    [2] The effects of the introduced technology in achieving its objectives ( reduction in CO2 emissions in this case ) must be directly measurable and directly MEASURED.

    However wind, tide, wave and solar electricity generating technologies do not result in the pro rata elimination of CO2 emissions by fossil fuelled generators because their intermittency and unreliability means the latter have to be maintained in service (and operated inefficiently).

    Moreover there are not even any attempts made to measure the effectiveness of the technologies. To do so needs measurement not only of CO2 emissions savings made by operating the introduced technology but also a comparison of CO2 emissions on a full life cycle basis of the introduced technology AND the replaced technology.

    In the end it is all depressingly human!

    The politicisation of the scientific investigations, the environmental framing of the issues, the advocacy of ideologues, the veniality of political action and the rapacity of business exploitation of opportunity are all par for the course.

    The main concern I is that it is very unwise to interfere in large, poorly understood, economically, environmentally and socially important, naturally interacting systems as the outcomes are quite unpredictable and the there can be little reason for confidence that intervention will on balance be beneficial.

    Older posts «